OBTAINING THE NECESSARY BUILDING PERMITS
Procedure ¹ |
Kind of procedure (for 2006) |
Duration of procedure (days) |
Costs (in BGL) |
Where? |
|
|
Obtaining plots - parts of an existing Detailed Urban Development Plan (on paper) |
|
Size À4 - 15 BGL |
Dobrich Municipality |
|
2 |
Submitting an investment plan to be approved by the chief architect (with preliminary assessment) |
Up to 7 |
Buildings: |
|
|
3 |
Submitting an investment plan to be approved by the chief architect (without a preliminary assessment) |
Up to 30 |
Buildings: |
Dobrich Municipality |
|
|
Obtaining a project permit from the Water Supply and Sewage Company |
|
|
Water Supply and Sewage Company Dobrich |
|
5 |
Obtaining the approval of the Power Supply Company |
Up to 3 |
By the price list of Power Distribution - Varna Ltd.
|
Power Distribution - Varna Ltd Customer service centre in Regional Centre - Dobrich |
|
|
Obtaining the approval of Bulgarian Telecommunications Company (BTC) |
|
|
|
|
|
Approval by the Regional Office for Fire Safety and Protection of the Population (ROFSPP) |
|
Only for I and II category sites, in accordance with Tariff No. 4 - state fees and fees collected by the Ministry of Internal Affairs |
ROFSPP - Dobrich |
|
|
Approval of an investment plan by the Regional Inspectorate for the Protection and Control of Public Health (RIPCPH) |
|
|
|
|
|
|
|
|
Regional Environment and Water Inspectorate - Varna |
|
|
|
|
|
Regional Environment and Water Inspectorate - Varna |
|
11 |
The municipality issues a building permit |
Up to 14 |
For buildings from I to III category Total Floor Area (TFA) /ì2/x 300 BGL x 0.004 For IV category buildings TFA /ì2/x 300 BGL x 0.003 For V category buildings TFA /ì2/x 200 BGL x 0.002 For VI category buildings TFA /ì2/x 100 BGL x 0.002 |
Dobrich Municipality |
|
12 |
Signing a contract with an independent organization to supervise the implementation of the project (construction supervision company) |
Up to 7 |
From 150 to 3000 BGL |
The construction supervision company which is a party under the contract |
|
During construction works |
|||||
13 |
The supervising organization (construction supervision company) informs the municipality upon completion of the excavation works |
Up to 1 |
|
The construction supervision company which is a party under the contract |
|
14 |
Check after completion of construction and assembly works (the purpose of the check is to compare the foundations with the construction documentation and the Detailed Urban Development Plan) |
Up to 3 |
Building area: |
Dobrich Municipality |
|
15 |
Entering the building in the cadastre |
Up to 30 |
250 - 400 BGL |
Licensed Land Survey Company |
|
After the completion of construction works |
|||||
|
|
|
|
The construction supervision company which is a party under the contract |
|
|
The Chief Architect issues a certificate for building commissioning |
|
|
Dobrich Municipality |
|
|
Signing a preliminary contract with the Water Supply and Sewage Company |
|
|
Water Supply and Sewage Company - Dobrich |
|
19 |
Signing a preliminary contract with the Power Supply Company |
Up to 1 |
Free of charge |
Power Distribution - Varna Ltd Customer service centre in Regional Centre - Dobrich |
|
|
Signing a preliminary contract with the Bulgarian Telecommunications Company (BTC) |
|
|
|